1. Project Outline
1-1 Project Title
1-2 Project Objectives
1-3 Project Procedures
1-4 Project Outline
1-5 Expected Effect
2. Project Schedule and Implementation Method
2-1 Premise of the Study
2-2 Implementation and Flow of the Project
2-2-1 Project implementation
2-2-2 Procedures of the project
2-2-3 Project work plan & performance
2-3 KEPCO Project Team Organization and Staffing Schedule
2-3-1 Organization
2-3-2 Staffing schedule
2-4 Report Submit and Seminar
2-4-1 Report submit
2-4-2 Seminar
2-5 Counterpart Staffs
II Electric Power Industry in Indonesia
1. Electric Power Industry in Indonesia
1-1 Basic Structure of the Electric Power Industry
1-2 General Status of PLN
1-2-1 Customer
1-2-2 Generation
1-2-3 Transmission & substation
1-2-4 Distribution
2. General Condition of Project Site
2-1 General Weather Conditions of Indonesia
2-2 Distribution Organization
2-2-1 Central Java
2-2-2 East Java
2-2-3 Bali
2-3 Present Condition of Sales
2-3-1 Central Java
2-3-2 East Java
2-3-3 Bali
2-4 Power Demand
2-4-1 Central Java
2-4-2 East Java
2-4-3 Bali
2-5 Situation of Facility Operation
2-5-1 Distribution facility composition and features
2-5-2 150/20kV substation
2-5-3 20kV Service entrance facility for medium voltage customer
2-6 Maintenance System of Distribution Facility
2-6-1 Fault recovery system
2-6-2 Implementation of distribution construction
2-6-3 Distribution facility information system
2-6-4 Procurement system for distribution material
2-7 Distribution Maintenance System
2-7-1 Dispatch Control Center (DCC)
2-7-2 Distribution Operation Center (DOC)
2-7-3 Hot line work team (PDKB)
2-7-4 Substation Patrol Unit (Mobile Unit)
2-7-5 Construction and maintenance contractor
2-7-6 Activities to prevent interruptions
3. Analysis of Distribution Line Interruption
3-1 Semarang
3-1-3 Interruption analysis by cause
3-1-4 Interruption analysis by substation and feeder
3-1-5 Interruption analysis by interruption frequency and duration
3-2 Surabaya
3-2-1 Outage statistics management
3-2-2 Interruption analysis by month
3-2-3 Interruption analysis by cause
3-2-4 Interruption analysis by substation and feeder
3-3 Bali
3-3-1 Outage statistics management
3-3-2 Interruption analysis by year and month
3-3-3 Interruption analysis by cause
3-3-4 Interruption analysis by substation and feeder
3-4 Consolidation of Fault Analysis
3-4-1 Semarang
3-4-2 Surabaya
3-4-3 Denpasar
4. Measurement & Analysis of Supply Reliability
4-1 Detail of Measurement
4-1-1 Semarang
4-1-1 Surabaya
4-1-3 Denpasar
4-2 Analysis of Measured Data
4-2-1 Semarang
4-2-2 Surabaya
4-2-3 Bali
III Improvement of Reliability
1-1 Reliability
1-2 Necessity of Reliability at Distribution System
1-3 Factors Affecting to Reliability
1-4 Interruption Statistics Management
1-4-1 Purpose of interruption records & interruption statistics management
1-4-2 Interruption classification
1-5 Overview of Reliability Management Worldwide
2. Establishment of Systematic Interruption Statistic Management System
2-1 Use International Standard Reliability Index
2-2 Analyze Cause of Interruption
2-3 Recommendation on Interruption Classification
2-4 Input Data & Implement Reliability Management System
2-5 Utilization of Interruption Statistics Management Program
2-6 Introduction of Root Cause Analysis System
2-7 Important Customer Interruption Detection & Automatic Notification System
3. Improvement of Fault Prevention
3-1 Prevention of Tree Contact
3-1-1 Tree trimming
3-1-2 Partial use of insulated wire & aerial bundled cable
3-1-3 Use of curved steel pole
3-2 Surge Arresting Arrangement
3-2-1 Concept of lightning
3-2-2 Installation of overhead ground wire
3-2-3 Installation of surge arrester
3-2-4 Concurrent installation of overhead ground wire and surge arrester
3-3 Improvement of distribution Line Patrol, Inspection & Measurement
3-3-1 Distribution line patrol
3-3-2 Distribution line inspection
3-3-3 Distribution line measurement
3-4 Use Facility Diagnosis Instruments Actively
3-5 Improvement of Protective Coordination System
3-6 Preventing the Theft of Grounding Wire & Neutral Conductor
3-7 Preventing Faults Attributable to Facilities of Customer, Other Company
3-7-1 Outline of propagation fault
3-7-2 Conducting preventative diagnosis of power-receiving facilities of high-voltage customers
3-8 Preventing CSP Transformer Failure
3-9 Improving 20kV Bus Type
4. Establishment of Quick Fault Recovery Process
4-1 Material Management for Emergency Maintenance
4-2 Establishment of Electrical Facility Monitoring System
4-3 Establishment of Permanent Emergency Mobilization Process
4-4 Contractor Management
4-4-1 High voltage contractor
4-4-2 Underground contractor
4-4-3 Low voltage contractor
4-4-4 Ex-post management
4-5 Improvement on Operation System of Distribution Control Center
4-6 Improvement on Operation System of Distribution Operation Center
5. Recommendation to Improve the Distribution Operation System of PT PLN
5-1 Distribution Feeder Configuration
5-1-1 Distribution feeder interconnection and division
5-1-2 Examples of Improving Distribution feeder configuration
5-2 Implement Distribution Automation System (DAS)
5-3 Improvement of Operation Scheme for Distribution Information System (DIS)
5-3-1 Facility information and data management
5-3-2 Drawing management
5-4 Recommendation to Reduce Scheduled Interruption
5-4-1 Hot line work
5-4-2 Non-interruption work method
5-4-3 Recommendations for reducing scheduled interruption
5-5 Security of Maintenance Budget for Distribution Facility Maintenance
5-6 Improve Efficiency Distribution Planning
5-7 Reliability Improvement through Improving the Quality of Materials and Equipment
5-7-1 Material procurement in Indonesia
5-7-2 Reliability improvement through improving the quality of materials and equipments
5-8 Construction Underground Distribution Feeder
5-9 Building up Distribution Department and Hiring New Employees
6. Analysis of Investment Effect in Reliability
6-1 Interruption Cost
6-1-1 Definition of interruption cost
6-1-2 Optimization of reliability
6-1-3 Effects of electric company by the interruption
6-1-4 Interruption cost of Indonesia
6-2 Effect by the Reliability & Power Quality Improvement Strategies
6-2-1 Division & interconnection of power system
6-2-2 Introduction of facility degradation diagnostic instruments
6-2-3 Insulation of overhead line
6-2-4 Comprehensive analysis of return on investment
1-1 Purpose
1-2 Scope
1-2-1 Installed system : Slim-type TDAS
1-2-2 Components of system
1-3 Participated Staff
2-1 System Outline
2-2 Components of TDAS
2-2-1 Main server
2-2-2 Communication facility
2-2-3 FRTU
2-2-4 Switches and controller
2-2-5 Simulator
2-2-6 Application program
3. Progress Report of Pilot Project
3-1 Work Classification
3-2 Progress Schedule
4-1 Pilot Project Design and Make a Contract (2006. 11)
4-2 Object Selection for Installation of Switches
4-3 Measuring and Examination
4-3-1 Grasping communication status & measuring (2006. 10 – 2006. 11)
4-3-2 Communication method examination & conclusion (2006. 10 – 2006. 11)
4-3-3 Facility technical examination (2007. 1)
4-4 Material Delivery and Transportation
4-4-1 Material purchase and inspection (2006. 12 – 2007. 01)
4-4-2 Transportation and customs clearance (2007. 01 – 2007. 02)
4-5 Switch construction
4-6 Communication Normality
4-6-1 Progressing process with GSM modem
4-6-2 Communication configuration
4-7 DB Construction (April 16th-20th, 2007)
4-8 Main Server Installation (April 17th, 2007)
4-9 Operation Test
4-9-1 1th operation test (May 4th-5th, 2007)
4-9-2 The 2nd operation test (June 15th-22nd, 2007)
4-10 Operator and Manager Training
4-10-1 The 1st training session (May 1st-5th, 2007)
4-10-2 The 2nd training session (June 18th-20th, 2007)
4-11 DAS Operator Manipulation Capability Evaluation
4-11-1 Key evaluation items
4-11-2 Evaluation results
4-12 Trial Run (July – October 2007)
4-12-1 Communication status and success rate
4-12-2 Fault indicator accuracy & fault description
4-12-3 Protection coordination confirmation
4-13 TDAS Completion (2007. 10. 30)
5. Analysis of DAS Introduction Benefits
5-1 Quantitative Benefits of TDAS Introduction
5-1-1 Decrease in supply failure
5-1-2 Reduction of loss in high voltage distribution line
5-1-3 Suppression of distribution line construction requirement
5-1-4 Saving operational costs
5-1-5 Extension of substation cb service life
5-2 Qualitative Benefits of TDAS Introduction
5-2-1 Improvement of responsiveness to fault
5-2-2 Acquisition of line information assures optimization of distribution system operation efficiency
5-2-3 Advancement of distribution electrical engineer’s work quality
5-2-4 Scientific distribution line system operation
5-2-5 Prevention of customer complaint & improvement of service quality
5-3 Conclusion
6. Difficult Things in Progressing
6-1 Frequent Change of Communication Process(CSD –> SMS –> GPRS)
6-2 Differency of Installation Method
6-3 Frequent Earthing Pilferage
6-4 Unstable Wireless Communication Network
6-4-1 Communication environment in Semarang
6-4-2 Results of communication environment analysis
6-4-3 Resolutions
7. Necessary Complementary Measures
7-1 Independent Power Security
7-2 Durable Management For Earthing
7-3 Managing Staff Expansion
7-4 Unified Lock Using for Control Box
7-5 Promoting Business Communication with Communication Carriers
7-6 Checking & Maintaining Communication Status & Facilities Regularly
7-7 Adjusting Switch Setting Following System Change
7-8 Realigning the Direction of Switch Control Box
7-9 Considering Transition to Other Communication Platform
7-10 Reinforcement for Distribution Line Patrol and Examination
1. Object
2. Training Schedule
3. Training Program in Korea
4. Training Program in Indonesia
5. Training Result
Alternatif artikel yang menarik lainnya:
- APP Terpadu Materi SPLN – Bagian 6
Materi dari Forum Distribusi 2007 (Denpasar, 31 Oktober – 1 Nopember 2007) Slide 13 Slide 14 Slide 15 Slide 16 Slide sebelumnya Kembali ke daftar isi artikel ini Download dokumen Power Point dari artikel ini - Kabel Berisolasi dan Berselubung PVC Tegangan Pengenal 300/500 Volt (NYM) – SPLN 42-2: 1992 – Bagian 9
Tabel IV: Faktor koreksi suhu untuk resistans isolasi Pasal SembilanSYARAT LULUS UJI 30. Syarat Lulus Uji 30.1. Uji Servis Uji jenis kabel jenis tertentu dianggap lulus, apabila contoh uji kabel jenis tersebut lulus semua mata uji jenis (J) tersebut pada Tabel II. 30.2. Uji Contoh Uji contoh untuk menilai sekelompok kabel jenis tertentu dianggap lulus, apabila contoh uji yang diambil dan setelah mengalami mata - Aliran Daya – Bagian 10
Slide 25 Slide 26 Slide 27 Slide sebelumnya Slide berikutnya Kembali ke daftar isi artikel ini Download dokumen Power Point dari artikel ini - Daftar Anggota Portal Jendela Distribusi – Bagian 16
Agus Isranto (UJ Madiun Kota) Bagio Soewarno (UJ Madiun Kota) Bambang Triwahyu AP (UJ Madiun Kota) Eko Sukarmin (UJ Madiun Kota) Hartanto (UJ Madiun Kota) Kabul Samingan WS (UJ Madiun Kota) Nanok Siswahyudi (UJ Madiun Kota) Paulus Edy Priyono (UJ Madiun Kota) Prasetijo (UJ Madiun Kota) Prenggo Widjono (UJ Madiun Kota) Sudiro (UJ Madiun Kota) Alamsyah (UJ Malang) Joko Suryanto (UJ Malang) Kusmadi (UJ Malang) Kusnan (UJ Malang) M Faisal - Pola Pengamanan Sistem Bagian 3: Sistem Distribusi 6 kV Dan 20 kV – SPLN 52-3: 1983 – Bagian 45
Lampiran H, ayat 2 (Lanjutan 2) Dengan demikian pada saat terjadi gangguan satu fasa ke tanah, sirkit ekuivalent rangkaian arus dan tegangan yang masuk kerelai arus lebih terarah menjadi seperti pada gambar 5a, sedang vektor arus dan tegangannya yang melalui relai seperti gambar 5b. Gambar 5 Bila hanya ditinjau arus resistifnya atau If besarnya : Karena m sangat tinggi


Berikan tanggapan
Anda harus logged in untuk memberikan tanggapan.